Office for Nuclear Regulation

Hinkley Point C – Inspection ID: 22-014

  • Site: Hinkley Point C
  • IR number: 22-014
  • Date: July 2022
  • LC numbers: 19

Executive summary

Purpose of Intervention

In accordance with the Office for Nuclear Regulation’s (ONR’s) Hinkley Point C (HPC) construction inspection plan, ONR performs a series of planned compliance inspections of applicable licence conditions. This is to ensure that the licensee, NNB Generation Company (HPC) Ltd (NNB GenCo), is adequately developing and implementing its compliance arrangements in a manner that is commensurate with the stage of the project under consideration.

This intervention was an inspection carried out to assess NNB GenCo’s compliance with licence condition 19 (LC19); construction or installation of new plant. LC19 requires that where the licensee proposes to construct or install any new plant, which may affect safety, the licensee makes and implements adequate arrangements to control the construction or installation.

Intervention Aim

The aim of this intervention was to assess the implementation of NNB GenCo’s arrangements in place for the installation of structural steel under LC19 for the control of civil engineering works.  Specifically, this intervention examined in some detail, the licensee’s implementation of its arrangements with regards to material conformance, quality management, fabrication and erection of structural steel elements, in accordance with the design intent and relevant good practice.

Explanation of Judgement if Safety System Not Judged to be Adequate

This section is not applicable as this was not a safety system inspection.

Key Findings, Inspector’s Opinions and Reasons for Judgements Made

Responses to questioning were forthcoming, constructive, and provided confidence that structural steel installation, where sampled, was being adequately managed with due consideration of the risks involved. A small number of minor observations were made.

Overall, I was satisfied with the adequacy of NNB GenCo’s ongoing structural steel installation arrangements.

Conclusion of Intervention

On the basis of the evidence sampled, and in recognition of progress to date, I was satisfied that the arrangements in place comply with LC19. Accordingly, I assign an inspection rating of GREEN (No formal action) to this intervention. No regulatory issues were raised.